Debated in Parliament on 5 Feb 2013.
Mr David Ong asked the Minister for National Development (a) what is the number of Lift Upgrading Programmes (LUP) that has exceeded the stipulated time of completion; and (b) in each of these cases, what are the reasons for the delay.
Most Lift Upgrading Programme (LUP) projects are completed ahead of schedule. Last year, 12 projects were, however, delayed. There were three main causes for the delay. First, mid-way through some projects, the residents asked to modify the scope of work and for additional items to be included. Second, while the projects benefit most residents, they may affect some residents, for example, in blocking their view. Additional time was then required to consult the affected residents in order to resolve such competing interests among residents. Finally, in some projects, the service providers encountered some unforeseen site constraints and took more time to complete the underground services diversion works.
In all such situations, HDB will work with the contractors to minimise the delay. As a last resort, HDB may have to seek the Working Committee’s approval to revise the Estimated Completion Date. Residents will then be informed of the revised date and the reasons for the revision.