Debated in Parliament on 4 Feb 2013.
Mr Laurence Lien asked the Deputy Prime Minister and Minister for Finance what measures are in place to ensure that there is sufficient procurement, project management and quantity surveying expertise such that the large public sector infrastructure projects are truly value for money.
Mdm Speaker, the Government's approach to maximising value-for-money in large public sector infrastructure projects is, first, to put in place systems and processes to optimise project design and cost efficiency; and second, to strengthen procurement and project management capabilities.
Let me touch on processes to optimise project design and cost efficiency. Madam, we introduced the MOF Gateway Process in 2010 to strengthen the rigour of the approval process for large development projects. Under this process, projects above $500 million in value are subject to a series of reviews – spanning concept, design and costs – by a Development Projects Advisory Panel (DPAP). The panel comprises senior public officers and industry practitioners with deep technical expertise and experience in major infrastructure development. In addition, large projects are also put through Value Management workshops to refine their design in order to maximise value and cost efficiency.
Madam, let me say something about how we strengthen public sector project management capabilities. Apart from this Gateway process, we are focusing on procurement and project management capabilities. Government agencies that undertake large infrastructure projects on a regular basis, such as the Land Transport Authority and JTC Corp, have dedicated units and staff overseeing the management of infrastructure projects. Over the years, they have built up substantial in-house capabilities in procurement and project
Page: 41
management.
To address the needs of Government agencies which do not have such expertise, the Centre for Public Project Management (CP2M) was set up in January 2011 with the aim of strengthening project management capabilities across the whole of Government. CP2M is staffed by experienced officers from various construction-related disciplines such as quantity surveying and project management. It provides advice and guidance to Government agencies both on design optimisation, as well as robust project management, including risk management. CP2M also helps agencies build their own capabilities in these areas and, in some instances, provides project management services directly to agencies upon request.
I would like to share an example to illustrate these points. This has to do with the Singapore University of Technology and Design. In order to promote and improve value-for-money, the Gateway review of the project, together with inputs from the CP2M team, helped to reduce the footprint of the campus, freeing up land for other uses. This was achieved through the re-routing of a service driveway and the relocation of the tennis courts to the roof of the indoor sports hall instead of on the adjacent grounds.
Finally, as part of a broader effort to ensure value-for-money in Government expenditure, the Value-for-Money Review Office under the Accountant-General's Department conducts reviews of completed infrastructure projects to identify learning points and best practices. The lessons learnt are shared with Government agencies, and contribute to building the public sector's capabilities in infrastructure development.
Thank you, Mdm Speaker. May I ask the Minister of State whether the measures she has outlined so far have in actual fact led to all or most infrastructure projects being completed with proper project management and prudent use of resources? Or in other words, is the Ministry satisfied with the progress so far? And this is given a lot of loss of project management and project planning capacity within the public service with the spin-offs of agencies like the Public Works Department and the Housing and Development Division previously, and also given that there have been some projects with quite large over-runs like the Downtown Line.
Madam, I would like to thank the Member for his supplementary questions. Since the Gateway process was started in 2010, we have put 26 large-scale projects through this process. These projects are still
Page: 42
on-going and we are tracking them closely. We are very interested, ourselves, to make sure that there are cost savings, but the actual cost savings will only be known at project completion.
Mr Lien has also raised the other point about capabilities being lost when sometimes departments are corporatised and so on. It is a very important matter, and although these capabilities no longer reside within the Government, it does not necessarily mean that the capabilities do not reside in Singapore. That is also an important factor to bear in mind.
Order. End of Question Time. Mr Pritam Singh
[Pursuant to Standing Order No 22(3), Written Answers to Question Nos 24, 26-28, 35, 37-38, 43-44, 49-50, 53, 55-58, 60-61, 63-64 and 66 on the Order Paper are reproduced in the Appendix. Question Nos 25, 29-34, 36, 39-42, 45-48, 51-52, 54, 59, 62 and 65 have been postponed to the sitting of Parliament on 5 February 2013.]