Noise Barriers for MRT Tracks at Khatib Station
- The Minister confirmed that the tender for noise barriers at Khatib and other Phase 2 locations will be called within months, with installation starting around 2020 and completion by 2022, following a delay due to a review of Phase 1 results and coordination with other rail works.
- Er Dr Lee Bee Wah highlighted a previous timeline that was delayed from 2019 to 2022 and urged prioritizing Khatib due to residents' sleep disturbances from noise.
- The Minister explained the delay was due to a budget review requiring Phase 2 to follow Phase 1 evaluation, and acknowledged the constituency's experience with similar Phase 2 delays.
- Alex Yam noted that Phase 1 in Yew Tee remains incomplete due to higher barriers being deferred to Phase 2, leaving residents concerned about prolonged partial installation.
- Both MPs emphasized the need for timely completion, and the Minister expressed sympathy and commitment to expedite the process.